The short answer
Supply only means Vitrova makes the windows and doors to the agreed sizes and delivers them; you or your installer fits them. In England, replacing windows or doors in a home is notifiable building work, and the person doing the fitting carries that responsibility. An installer registered with a competent person scheme such as FENSA or CERTASS notifies the council and you should receive a certificate of compliance within 30 days. If the fitter isn’t registered, you must submit a building notice or full plans application to a building control body and pay a fee before the work starts. Skipping this can mean unlimited fines, putting the work right at your own expense, and no certificate when you sell. The installation must meet the energy, ventilation, safety glazing and escape rules. Sizes come from you, your installer or a surveyor you arrange: Vitrova records which on the quotation and checks every size against the maker’s limits.
Who does what on a supply-only order
Responsibilities are set out on every Vitrova quotation. In outline:
| Task | Who |
|---|---|
| Specification, U-values, safety glass and vents shown line by line | Vitrova |
| Checking every size and layout against the manufacturer’s limits | Vitrova |
| Measuring the openings | You, your installer, or a surveyor you arrange (we can put you in touch with one) |
| Ordering, manufacture and delivery | Vitrova |
| Receiving and checking the delivery on site | You or your installer |
| Removing the old frames, fitting, sealing and making good | You or your installer |
| Notifying building control or self-certifying through a scheme | Your installer, or you |
Building regulations: notifying the work
Since April 2002 building regulations have applied to all replacement glazing in England. Replacing a window or door unit in a home has to be notified, either by a registered installer or by an application to building control before the work starts. The government lists these competent person schemes for replacement windows, doors, roof windows and rooflights in dwellings: ASSURE, Blue Flame, BM TRADA, BSI, CERTASS, Certsure, FENSA, NAPIT and STROMA.
If you are fitting the windows yourself, or using a builder who isn’t registered, apply to your council’s building control or a registered building control approver first. Keep the completion certificate with the house documents.
What the installation must meet
A supply-only order can include everything below; the installer has to make sure it ends up in the right place.
- Energy (Approved Document L): replacement windows 1.4 W/m²K or WER band B; doors 1.4 W/m²K or the energy rating route.
- Ventilation (Approved Document F): replacement trickle vents no smaller than the old ones; where there were none, about 8,000 mm² in habitable rooms and kitchens and 4,000 mm² in bathrooms, unless building control agrees otherwise.
- Safety glazing (Approved Document K): safety glass in any glazing up to 800 mm above the floor, in doors up to 1,500 mm, and in side panels within 300 mm of a door edge up to 1,500 mm.
- Means of escape (Approved Document B): a replacement escape window should be at least as good as the old one; the usual guide is a clear opening of at least 0.33 m², at least 450 mm wide and high, with the bottom no more than 1,100 mm above the floor.
- Security (Approved Document Q): new homes only, usually by PAS 24 tested products.
Who measures, and how sizes are checked
Every Vitrova quotation records its size basis: structural opening sizes, from which we take the fitting gap, or finished frame sizes. Before anything is ordered we check every opening against the manufacturer’s limits for that system and layout. If you would rather not take responsibility for sizes, arrange a check measure by a surveyor or your installer; we can put you in touch with a surveyor. The surveyor records each opening through the My Vitrova survey form and the quotation is revised to the surveyed sizes before you approve it. Our project in progress in south-west Surrey shows how much that can change.
Delivery and storage
Whoever receives the delivery checks the load against the delivery note and signs it off, noting any damage straight away. Store frames upright on bearers, out of the way of site traffic, and leave protective film on until fitting. Large glass and long doors can need a crane lorry and clear space at the kerb; we confirm what your delivery needs before the date is set.
Questions people ask
Can I fit replacement windows myself?
Yes, but you must apply to a building control body before you start and pay its fee, and the work is then inspected. A registered installer avoids that by self-certifying the work.
What happens if replacement windows aren’t notified?
The council has no record that the work complies. You could be prosecuted and face an unlimited fine, be made to put the work right at your own expense, and you may be asked for the certificate when you sell the house.
Does Vitrova fit windows and doors?
No. Vitrova supplies made-to-measure windows, doors and rooflights to builders, installers and self-builders. Sizes can be checked on site before anything is made by a surveyor you or your installer arrange; we can put you in touch with one.
Do supply-only windows come with a warranty?
The warranty for each product is stated on its product page and confirmed on your quotation; fitting is covered by your installer.
Next steps
Sources
- GOV.UK: Building work, replacements and repairs to your home
- Planning Portal: Doors and windows, building regulations
- LABC: Replacement windows and trickle vents (explains Approved Document F, 2021)
- GOV.UK: Approved Document K, Protection from falling, collision and impact
- GOV.UK: Approved Document B (fire safety), Volume 1: Dwellings
- GOV.UK: Approved Document L, Volume 1: Dwellings, 2021 edition (PDF), Tables 4.1 and 4.2
- GOV.UK: Approved Document Q, Security: Dwellings, 2015 edition (PDF)
This guide covers England and is general information, not a substitute for advice from your building control body or planning authority on a particular project.